Value | Category | Cases | |
---|---|---|---|
1 | Grid is too far from household/not available | 1029 |
33.7%
|
2 | Cost of initial connection is too expensive | 1152 |
37.7%
|
3 | Monthly fee is too expensive | 37 |
1.2%
|
4 | Satisfied with current energy solution | 6 |
0.2%
|
5 | Renting, Landlord decision | 81 |
2.6%
|
6 | Service unreliable | 16 |
0.5%
|
7 | Administrative procedure is too complicated | 15 |
0.5%
|
8 | Submitted application and waiting for connection | 148 |
4.8%
|
9 | Company refused to connect the household | 41 |
1.3%
|
10 | Lack of political will/enabling policies for integration of refugees in national | 281 |
9.2%
|
11 | National grid or formal connection is not permitted or illegal | 7 |
0.2%
|
555 | Other, specify | 244 |
8%
|
Sysmiss | 2649 |